Can I Get Project Schedule Details for Sattva Aangane?

Yes, you can get the full project schedule for Sattva Aangane from its K-RERA filing. Work starts on 1 October 2026, and the proposed completion date is 21 October 2032. The filing gives a start and end date for every task, from digging the basements to painting and landscaping. Anyone can view it free on the Karnataka RERA portal under registration number PRM/KA/RERA/1251/446/PR/180926/008944.
Below, we lay out that schedule stage by stage. We also explain what you should see on site each year.