Can I Get Project Schedule Details for Sattva Aangane?

Featured Image of Can I Get Project Schedule Details for Sattva Aangane?


Yes, you can get the full project schedule for Sattva Aangane from its K-RERA filing. Work starts on 1 October 2026, and the proposed completion date is 21 October 2032. The filing gives a start and end date for every task, from digging the basements to painting and landscaping. Anyone can view it free on the Karnataka RERA portal under registration number PRM/KA/RERA/1251/446/PR/180926/008944.

Below, we lay out that schedule stage by stage. We also explain what you should see on site each year.

What Are the Key Dates for Sattva Aangane?


Milestone Date as filed
BDA plan approval 2 February 2026
RERA registration 18 September 2026
Construction start 1 October 2026
Proposed completion 21 October 2032

Some ads and listing pages still quote possession in 2029, 2031 or September 2032. None of these match the filing. The RERA date of 21 October 2032 is the one that holds legal weight for you as a buyer.

Stage-Wise Construction Schedule


The filing splits the work into three stages. Sub-structure covers everything below ground, super-structure covers the towers you can see, and finishing covers the final fittings.

Stage Work Start End
Sub-structure Earthwork and levelling 1 Oct 2026 2 May 2028
Sub-structure Foundation and footing 1 Apr 2027 1 Sep 2028
Sub-structure Work up to plinth level 1 Apr 2027 31 Jul 2029
Sub-structure Retaining walls 1 Apr 2027 31 Jul 2029
Sub-structure Basement and parking floors 26 Nov 2028 31 Jul 2030
Super-structure RCC frame 29 Jun 2028 19 Apr 2032
Super-structure Masonry 29 Jun 2029 25 Mar 2032
Super-structure Plastering 27 Sep 2029 2 Jun 2032
Super-structure Doors, windows and ventilators 22 Sep 2029 4 May 2032
Super-structure Basic water, sanitary and electrical work 27 Sep 2029 14 Apr 2032
Super-structure Railings and grills 2 Jan 2031 15 Sep 2032
Super-structure Flooring, skirting and tiles 2 Apr 2031 22 Sep 2032
Finishing Weatherproofing 27 Oct 2029 4 May 2032
Finishing Fire safety network 27 Dec 2029 22 Sep 2032
Finishing Final water, sanitary and electrical fittings 2 Apr 2032 22 Sep 2032
Finishing Painting 2 May 2032 15 Sep 2032
Finishing Elevation work 2 May 2032 5 Sep 2032
Finishing Landscaping and outdoor works 1 Aug 2029 21 Oct 2032

Why Does Sattva Aangane Take Six Years to Build?


Six years can feel long, but the scale of the project explains most of it. Every tower sits on four basement levels, and that digging alone runs for about eighteen months. Tower 7 rises to 42 floors and 143 m, so its frame alone takes several years to complete. The filing also lists a total built-up area of about 22.7 lakh sq ft across five towers.

A tall frame has to go up one floor at a time, with each slab curing before the next one starts. That is why the RCC work alone runs from June 2028 to April 2032 in the filed schedule.

What Will You See on Site, Year by Year?


A table of dates can feel abstract, so here is what the schedule means on the ground.

2026 and 2027: The site will look like a large dig. Earthwork starts in October 2026, and foundations and retaining walls begin in April 2027. Each tower needs four basement levels, so this phase takes longer than in most projects.

2028: Foundations wrap up by September 2028. The RCC frame starts in June 2028, so you should see the first columns rise above ground. Basement floor work begins in November 2028.

2029 and 2030: This is the busiest stretch. Masonry starts in June 2029, and plastering, doors, windows and basic plumbing follow from September 2029. Landscaping starts in August 2029, and the basement floors finish by July 2030.

2031: The towers keep climbing while flooring and tile work begins inside the lower floors from April 2031. Railings and grills start going in from January 2031.

2032: The RCC frame finishes in April 2032, with Tower 7 the last to top out at 42 floors. Painting, elevation work and final fittings run from April to September 2032. Landscaping closes out on 21 October 2032, the filed completion date.

What Does the Schedule Include and Leave Out?


The filing commits the promoter to deliver the site infrastructure within this same timeline. That covers water supply, sewage lines, storm water drains and a sewage treatment plant. It also covers rainwater harvesting, a transformer, street lights, internal roads and fire safety systems.

Wardrobes, showcases and kitchen cabinets are marked as not included. You will need to budget for these and fit them yourself after handover.

How Does the Schedule Protect Your Payments?


Most buyers pay through a plan linked to construction stages. Each demand letter should match a stage the site has actually reached, and the table above lets you check this yourself.

The filing also lists a dedicated project bank account with ICICI Bank. Under RERA, the promoter must keep 70% of buyer payments in a separate account for this project alone. That money can only go towards land and construction costs for Sattva Aangane.

Who Is Building Sattva Aangane?


Starworth Infrastructure and Construction Limited, a Puravankara company, holds the building contract. Puravankara disclosed a Letter of Intent worth about ₹311.18 crore for this project in January 2026, with a 37-month contract period. That period covers the contractor's own scope of work. For you as a buyer, the binding date is still the RERA completion date of 21 October 2032.

How Can You Track Progress After Booking?


RERA asks every promoter in Karnataka to upload a progress report each quarter. These steps help you compare real progress with the filed schedule.

  • Search the registration number on rera.karnataka.gov.in and open the project page.
  • Download the latest quarterly progress report and match the finished tasks with the dates above.
  • Check each payment demand against the stage marked complete in that report.
  • Visit the site every few months, or ask the sales team for dated photos of each tower.
  • Keep a short note of every visit, so you can raise any gap early and in writing.

Is This Timeline Right for You?


A six-year build suits buyers who do not need to move in before late 2032. If you are an investor, you get time to pay in stages. During this time, the Old Madras Road belt and the PRR will keep developing around the site. If you need a home sooner, nothing in the filing supports an earlier handover, so plan around October 2032.

If the promoter misses the registered date, the RERA Act lets you claim interest for the delay or ask for a refund. Keep your agreement, receipts and demand letters safe for any future claim. To see how the five towers and open spaces come together by 2032, visit the Sattva Aangane Master Plan page.

FAQs


1. When does construction of Sattva Aangane start?

The K-RERA filing lists 1 October 2026 as the start date, beginning with earthwork and levelling of the site.

2. What is the RERA completion date of Sattva Aangane?

The proposed completion date in the RERA filing is 21 October 2032. This is the date that holds legal weight for buyers.

3. When can I expect possession in Sattva Aangane?

Plan for possession after 21 October 2032, the filed completion date. Earlier dates quoted in some ads do not match the filing.

4. Where can I check Sattva Aangane construction status?

Search PRM/KA/RERA/1251/446/PR/180926/008944 on rera.karnataka.gov.in and open the latest quarterly progress report.

5. Which company is building Sattva Aangane?

Starworth Infrastructure and Construction Limited, a Puravankara company, holds the main building contract for the project.

6. What happens if Sattva Aangane gets delayed?

The RERA Act lets you claim interest for each month of delay, or ask for a refund if the promoter misses the date.